COMPARATIVE ANALYSIS OF WORK PRODUCTIVITY THROUGH THE OVERALL EQUIPMENT EFFECTIVENESS (OEE) METHOD
DOI:
https://doi.org/10.46306/bbijbm.v4i3.113Keywords:
Work Productivity, Overall Equipment Effectiveness (OEE) MethodAbstract
In an effort to increase employee work productivity, not only rely on the quality of the products produced, but companies or institutions also need to pay attention to factors that influence employee work productivity at PT. XYZ Serang Banten, such as labor and the work environment. Labor is one of the factors that contributes to increasing productivity, with quality labor the production process activities will run as expected by the company, if the labor does not work well then the production process will be disrupted and the results achieved by the company will not be optimal or less productive. By paying attention to factors that can influence the level of employee work productivity, companies can better know and understand the needs and desires of their employees so that employees can feel more satisfied or more cared for and can carry out their work activities optimally.
The aim of the research is to compare productivity between work teams in the assembling division PT. XYZ Serang Banten using the OEE (Overall Equipment Effectiveness) method. Where the results per lot that have been worked on are recorded and entered into the OEE data table.
The method used in collecting this data is a descriptive method, where the problem solving procedure that is investigated is by describing the condition of the subject or object in the research, which can be people, institutions, society and others which are currently based on visible facts or what they are. This method carried out through surveys, where investigations are carried out to obtain facts from existing phenomena and seek factual information, whether about the social, economic or political institutions of a group or region. And the type of data is qualitative because this data can use words to describe facts and phenomena observed from primary data obtained through interviews and observations.
The research results of each team of the 3rd shift assembling division PT. XYZ Serang Banten on the preparation of kraft and decor paper which the operators arranged for one month using the OEE method calculation results were an average productivity of 70%. The highest average productivity was obtained by team C with a total average productivity of 74% , and 73% was obtained by teams B and D. Meanwhile, the lowest average productivity was obtained by team A
Downloads
References
Assauri, Sofjan. (2016). Manajemen Operasi Produksi : Pencapaian Sasaran Organisasi Berkesinambungan, Edisi 3, PT. Raja Grafindo Persada, Depok.
Diandra Maulidina, Astrid, Erry Rimawan, & Muhammad Kholili, (2016), Analisa Total Productive Maintenance Terhadap Produktivitas Kapal/Armada Menggunakan Metode Overall Equipment Effectiveness Pada PT. Global Trans Energy International, Journal of Industrial Engineering & Management Systems, JIEMS , Vol. 9, No 1, February 2016
Dwi Cahyono, Sigit, Fourry Handoko & Nelly Budiharti, (2020), Penerapan Efektivitas Mesin Debarker Menggunakan Overall Equipment Effectiveness (Studi pada PT. Tri Tunggal Laksana Unit Blitar), Jurnal Teknologi dan Manajemen Industri, Vol. 6 No. 2, Agustus 2020
El-Dairi, M., & House, R. J. (2019). Optic nerve hypoplasia. In Handbook of Pediatric Retinal OCT and the Eye-Brain Connection (pp. 285–287). https://doi.org/10.1016/B978-0-323-60984-5.00062-7
Hafiz Khoirul & Erwin Martianis, (2019), Analisa Overall Equipment Effectiveness (OEE) pada Mesin Caterpillar Type 3512B di PT. PLN (Persero) ULPLTD Bagan Besar PLTD Bengkalis, SINTEK JURNAL: Jurnal Ilmiah Teknik Mesin, Vol. 13 No. 2, Desember 2019.
Heizer, Jay, Barry Render, & Chuck Munson, 2017, Operations Management: Sustainability and Supply Chain Management, 12th Edition, Publisher : Pearson; 12th edition (January 21, 2016)
Herjanto, Eddy, (2007), Manajemen Operasi, Edisi 3, Grasindo , Jakarta:
Hesti Triwardani, Dinda, Arif Rahman, & Ceria Farela Mada Tantrika, (2013), Analisa Nilai Overall Equipment Effectiveness (OEE) dalam Meminimalisi Six Big Losses pada Mesin Produksi Dual Filer DD07, (Studi kasus : PT. Filtrona Indonesia, Surabaya, Jawa Timur), Jurnal Rekayasa dan Manajemen Sistem Industri, Vol. 1 No. 2 (2013)
Lukmandono, Enik Sulistyowati, Ni Luh Putu Hariastuti, Pendekatan Overall Equipment Effectiveness dan Response Surface Methodology dengan Pertimbangan Root Cause Failure Analysis untuk Meminimalkan Six Big Losses, https://id.scribd.com/document/623301269/1439-3766-1-SM
Maitsa Zulfatri, Muthi, Judi Alhilman, & Fransiskus Tatas Dwi Atmaji, (2020), Pengukuran Efekivias Mesin dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) dan Overall Resources Effectiveness (ORE) pada Mesin PL1250 di PT.XZ. JISI: JURNAL INTEGRASI SISTEM INDUSTRI, Volume 7 No 2 Agustus 2020
Mustaqimah, Atika, (2009), Pengukuran Nilai Overall Equipment Effectiveness (OEE) sebagai Dasar Usaha Perbaikan Proses Manufaktur pada Lini Produksi (Studi Kasus pada PT Indo Furnitama Raya, Pasuruan), https://dspace.uii.ac.id/handle/123456789/18711
Oktaria Susanti, (2011), Perhitungan dan Analisa Nilai Overall Equipment Effectiveness (OEE) pada Proses Awal Pengolahan Kelapa Sawit (Studi Kasus PT X) , Program Sudi Teknik Industri, Universitas Indonesia, file:///C:/Users/User/Downloads/digital_20295993-S1813-Perhitungan%20dan-1.pdf
Rahman, Arif dan Surya Perdana, (2019), Analisis Produkivias Mesin Perceakan Perfec Binding dengan Metode OEE dan FMEA, Jurnal Ilmiah Teknik Industri (2019), Vol. 7 No. 1, 34 – 42
Reksohadiprodjo, Sukanto, & Indriyo Gitosudarmo, (1991), Manajemen produksi, ed. 4,cet.3, BPFE, Yogyakarta.
Suliantoro, Hery, Novie Susanto, Heru Prastawa, Iyain Sihombing, & Anita M., (2017), Penerapan Metode Overall Equipment Effectiveness (OEE) dan Fault Tree Analysis (FTA) untuk Mengukur Efektifias Mesin Reng, J@ti Undip: Jurnal Teknik Industri, Vol. 12, No. 2, Mei 2017
Tisnawati Sule, Ernie & Kurniawan Saefullah, (2017), Pengantar Manajemen (1st ed.). Kencana, Jakarta.
Wahid, Abdul, (2020), Penerapan Total Productive Maintenance (TPM) Produksi Dengan Metode Overall Equipment Effectiveness (OEE) Pada Proses Produksi Botol (PT. XY Pandaan – Pasuruan), Jurnal Teknologi dan Manajemen Industri, Vol. 6 No. 1, Februari 2020
Wuryanto, Abdul Wahid, (2018), Analisis Predictive Maintenance dengan Metode OEE (Overall Equipment Effectiveness) Guna Meningkatkan Performa pada Mesin Husky (PT. X Gempol), Journal Knowledge Industrial Engineering (JKIE), Vol. 5, No.1. 2018
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Abdul Rauf Chaerudin, Rayhan Abdurrasyad

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.